AMDA Rubaga Project Update

I. Current Status

The AMDA Rubaga Project commenced in 2015 and comprises:

  • A multipurpose hall
  • Office space for AMDA, ABF, and SACCO
  • A canteen
  • A four-level, 15-bedroom clergy residence

The initial budget for the complex was UGX 5.1 billion.

Currently:

  • The ground and first floors of the clergy residence are complete and occupied
  • The second and third floors, including the Archbishop’s suite, remain incomplete and uninhabitable
  • The main hall is still unfinished but has been in use since 24th November 2024 for Mass and meetings

To fast-track partial occupation, a UGX 200 million loan was secured from the AMDA SACCO in August 2024 at 17% interest per annum.

As of 25th March 2026:

  • Total paid: UGX 150,376,850
  • Outstanding balance: UGX 47,570,950

II. Works Completed Since November 2024

The following progress has been made:

  1. Timber tiling of the Archbishop’s suite (3rd floor)
  2. Completion of a 2-bedroom guard house (with water, electricity, tiling, fittings)
  3. Electrical wiring (first fix) for:
    • Main hall
    • Cafeteria
    • Office spaces
  4. Plastering of the main hall
  5. First coat of painting for the main hall
  6. Floor screeding of the main hall
  7. Ceiling works for cafeteria and office spaces
  8. Fabrication of steel balustrades for safety
  9. Loan repayment installments totaling UGX 150,376,850

III. Pending Works to Completion

A. Clergy House

Pending items include:

  • Steel window frames, glazing, and sealing
  • Painting (2nd and 3rd floors)
  • Tiling (2nd floor)
  • Doors installation
  • Electrical wiring and fittings
  • Plumbing works

Estimated Total (A): UGX 211,826,000


B. Main Hall

Pending works include:

  • Steel windows
  • Steel balustrades
  • Doors installation
  • Floor tiling
  • Internal and external painting
  • External plastering
  • Electrical wiring and fittings
  • Mechanical piping and installations

Estimated Total (B): UGX 547,498,000


C. External Works & Auxiliary Expenses

Includes:

  • Landscaping, paving, and lighting
  • Water utilities
  • Electricity (UEDCL connection and bills)
  • Caretaker allowance
  • Boundary fencing
  • Drainage improvements

Estimated Total (C): UGX 129,332,000


D. Loan Repayment

  • Principal Balance: UGX 43,809,551
  • Interest Balance: UGX 3,761,399

Total Loan Balance (D): UGX 47,570,950


Grand Total Required

UGX 936,226,950


IV. Completion Plan

Through the generosity of AMDA members and friends, significant progress has been made. We are deeply grateful for all contributions.

Key Priorities

  • Clear the outstanding loan by September 2026
  • Resume full construction immediately after loan clearance

If each monthly animation raises UGX 10 million, the loan can be cleared comfortably within the timeline.


Special Appreciation

We extend sincere gratitude to:

  • Hon. Kobusingye Adrine
    (Chairperson – NRM Women League, Kyamuhunga Parish)
    • For offering to fund windows and doors for the multipurpose hall
  • All members who have contributed so far

Call to Action

We appeal to all members who made pledges during the “Tutaahe Rubaga” fundraiser (24th November 2024) to honor their commitments.

  • Only 46% of pledges have been fulfilled
  • Completing the remaining pledges will significantly accelerate progress

Closing Message

May God richly bless your generosity and commitment.

Turibamwe, omuri Kristo!


Eng. Anthony Rucukye
Chairperson, Construction Committee